Concrete · Driveway + Flatwork

Driveway + Walkway Replacement

A cracked, settled driveway demoed and re-poured on a properly compacted base, with a new walkway and a control-joint layout that will keep the slab honest for decades.

Finished concrete driveway replacement - Green O Construction
Location
Beaverton, OR
Size
Driveway + front walkway flatwork
Project type
Concrete flatwork replacement
Duration
About a week on site, plus cure time
Completed
Spring 2025
Credentialed scope
Demo and haul-off, subgrade preparation and compaction, forming, reinforcement, pour and finish, control joints, cure and seal

The challenge

The original driveway had done what unreinforced slabs on poor bases do: cracked where it wanted to, settled toward the garage, and started ponding water against the apron. Mudjacking had been tried once before we arrived; the slab settled again because the problem was never the slab. It was the base under it.

The owners wanted it done once. That meant demo, a real base, reinforcement, and a joint layout that decides where the concrete cracks instead of letting the concrete decide.

Concrete does not fail from the top down. It fails from the base up. The pour everyone sees is the easy part; the compaction nobody sees is the job.

Flatwork Lead, Green O Construction

Our approach

Demo first: the old slab broken, hauled, and the subgrade evaluated. The soft pockets that caused the settlement were dug out and rebuilt with compacted crushed rock in lifts, plate-compacted, and checked for grade so water runs away from the garage instead of into it.

Forms set the finished elevations and the drainage plan at the same time. Reinforcement went in on chairs so it lives in the middle of the slab, not on the dirt doing nothing. The pour was finished with a broom texture for wet-weather traction, edged clean, and jointed on a layout cut to depth so future cracking follows the lines we chose.

Then the part most people skip: cure. Concrete does not reach its strength on the day it looks done. We keep vehicles off flatwork for a full week and put that in writing at handoff, along with the reseal interval.

Completed concrete driveway, full view

Materials & specs

What we put on this house

Compacted crushed-rock base

Placed in lifts and plate-compacted after soft-pocket excavation

The base carries the load. Every settled slab we replace failed here first.

Steel reinforcement on chairs

Positioned mid-slab on chairs, not laid on the subgrade

Reinforcement only works where it sits. On the dirt it is decoration.

Exterior-grade concrete mix

Air-entrained mix appropriate for freeze-thaw exposure, broom finish

Air entrainment is what lets an Oregon slab shrug off freeze-thaw cycles instead of spalling.

Sawcut control joints + cure-and-seal

Joints cut to depth on a planned layout; membrane-cured and sealed

Concrete cracks. Joints decide where. Curing decides how strong it is when it does.

What was tricky

Grade was tight. The driveway had to fall away from the garage, meet the city sidewalk at its existing elevation, and still keep the walkway ADA-friendly at the entry transition. Forms were shot and re-checked twice before anyone saw a concrete truck.

Weather again: flatwork wants a dry pour day and a mild cure window. We held the pour date until the forecast cooperated rather than gambling a permanent surface on a passing shower.

Schedule

Week by week

  1. Day 1-2
    Demo + haul-off

    Old slab broken and hauled, subgrade evaluated, soft pockets excavated.

  2. Day 3
    Base + forms

    Crushed rock placed and compacted in lifts, forms set to drainage grades, reinforcement on chairs.

  3. Day 4
    Pour + finish

    Pour in a dry window, screed, float, broom finish, edges tooled, joints laid out.

  4. Day 5
    Joints + cure + seal

    Control joints cut to depth, cure applied, sealer per spec, barricades up for the cure week.

Process gallery

On the job

Concrete driveway pour in progress
Finished broom-finish concrete driveway
Completed concrete driveway, full view
New concrete walkway
Driveway and front elevation curb appeal
Retaining wall and hardscape detail

The result

Water now leaves the driveway the way the forms said it would. The joint layout has controlled cracking exactly as designed - hairlines in the cuts, nothing in the field. The broom finish grips in the rain and the sealed surface sheds the winter.

What we would tell any owner comparing flatwork bids: ask what happens below the slab. Thickness and PSI are on every quote. Compaction, reinforcement placement, joint depth, and cure discipline are the difference between the driveway that cracks in year two and the one that outlives the mortgage.

Credentials applied

Which licenses and certifications did the work

  • CCB #204939Flatwork, drainage grading, and demo carried under the general contractor license.
  • CESCL (Certified Erosion + Sediment Control Lead)Demo and excavation in a residential neighborhood run with documented erosion control.
  • OSHA 30Demo, excavation, and truck traffic managed under documented site-safety practice.

Want similar work?

We do this every week. Bring us the next one.

Free inspection. Honest scope. Warranty registered in your name.

Book Free InspectionCall (971) 226-7751

Disclaimer. Composite case study based on representative Green O projects. Client details anonymized; no individual client is identified. Material specifications reflect Green O’s standard install practice and may vary by project scope, code cycle, and manufacturer availability. CCB #204939 (Oregon). CertainTeed warranty terms are set by the manufacturer and registered per qualifying install. Photography from the Green O project archive; not necessarily from this specific composite project.

Topic cluster · Concrete and flatwork

More from the exterior and flatwork cluster.

Exterior services
Pillar overview - flatwork, drainage, envelope.
Contractor in Beaverton
Home turf - our HQ city.
Project gallery
More concrete and hardscape from the archive.
How we run a project
Scope, schedule, and cure discipline.
Free flatwork assessment
Base and drainage check before you re-pour.
Our credentials
CCB, CESCL, OSHA 30.
Call (971) 226-7751or text